National Epitaxy Facility

A new research facility on North Campus supporting advanced semiconductor research.

Steel frame of the new building
Off

About the project

The University is building a new clean room facility on the site previously occupied by modular buildings on North Campus. The building will provide a controlled environment for specialist epitaxy equipment used in semiconductor research. It is a specialist research building and will not be open to students or the public.

The facility will support the National Epitaxy Facility and the University’s research in advanced semiconductor materials. Epitaxy is a process used to grow extremely precise layers of crystalline material. These materials form the basis of many semiconductor technologies and can be used in areas including communications, sensing, energy and advanced electronics.

What we are building

The new facility will be a largely single-storey, double-height building containing a specialist clean room around five metres high. Its design is driven by the technical conditions needed to install and operate the research equipment safely and reliably.

The building has deliberately been designed as a practical and cost-effective temporary facility. Its dark grey external finish and simple form reflect its specialist function, while details have been refined through the planning process to respond to its surroundings.

Why the facility is temporary

The facility is an interim step that allows important new research equipment to be installed and used while the University develops its longer-term plans for research facilities. The project has been designed around a shorter anticipated operational need, with a steel frame that could be dismantled and reused or relocated when the facility is no longer required on this site.

Sustainability and energy use

Clean rooms require tightly controlled internal conditions and can be energy intensive. The project therefore includes energy-saving technology intended to reduce unnecessary operation when areas or systems are not in use. The building will also include a solar photovoltaic array. Its demountable steel structure has been selected with future reuse or relocation in mind, reflecting the building’s temporary role.

The project is reusing the foundations from the former Modular Village building, reducing the need for new concrete and the associated carbon emissions. It will also reuse the site’s existing power, data and drainage connections, reducing the new materials and carbon required for the development.

Construction and local impact

Construction activity is taking place within the existing site compound on North Campus. People nearby may see machinery operating and, as work progresses, the steel frame being assembled.

There are no planned tree removals associated with the project. External landscaping will be introduced in accordance with the University’s biodiversity palette.

Access to surrounding buildings and car parks remains open at present. Any temporary road closure or other change affecting the wider North Campus area will be communicated separately and added to this page in advance.

Project timeline

July 2026

Planning permission granted.

Late September to autumn 2026

Main construction begins, including erection of the steel frame.

May 2027

Building construction is expected to be complete, followed by installation and commissioning of the specialist research equipment.

Latest updates

28 September 2026 - work beginning on site

Work is beginning on the new epitaxy clean room facility on North Campus. Initial groundworks, including foundations and drainage, are under way. The steel frame is expected to begin rising shortly.

The work is contained within the construction site. Access and parking around North Campus remain open as usual at this stage. We will publish details here in advance if later phases require any temporary changes to nearby access.

2 July 2026 - planning permission granted

Sheffield City Council has granted planning permission for the temporary facility. The project team is now completing the process of discharging the pre-commencement planning conditions before the main structure is built.

The full planning application can be found on the Sheffield City Council planning portal here (Ref: 26/01020/FUL)

Keeping you updated

We will update this page at key stages of the project and publish advance notice of any work likely to affect access to nearby University buildings.

If you have any questions about the project, please email campusdevelopment@sheffield.ac.uk